Source: Government of Canada regional news
The Government of Yukon provides an update to Yukoners regarding the progress of the remediation work and environmental monitoring at the Eagle Gold heap leach failure.
On site, the berm is now 30 per cent complete. The pit pond extension is now complete adding 70,000 m3 of water storage bringing the total to 216,000 m3 built since the Receiver has been on site.