In the area of the village of Dorokhovo in the Moscow Region, construction of a transport interchange at the intersection of the M-1 Belarus highway and the A-108 Moscow Big Ring road continues. Builders have completed concreting the overpass superstructure. This was reported by Deputy Prime Minister Marat Khusnullin.
“In road construction, we pay special attention to transport interchanges. They improve the situation in complex transport hubs, solving the problem of traffic jams, as they redirect traffic flows without traffic lights and stops. In addition, they improve the throughput of roads, which is of great importance for high-speed highways. The construction of one of the interchanges continues at the 86th km of the M-1 “Belarus”. As of today, concreting of the superstructure of the overpass with a length of 95 m has already been completed. A total of 243 cubic meters of concrete and 200 tons of metal were used for this. The overall readiness of the facility is 85%,” said Marat Khusnullin.
The Deputy Prime Minister added that specialists will soon begin work on installing waterproofing, laying asphalt concrete, and installing a barrier fence and electric lighting lines. Earthworks on the site have been completed by 90%, during which 220 thousand cubic meters of sand, 51 thousand cubic meters of crushed stone and sand mixture were poured, and 152 thousand square meters of asphalt concrete were laid.
Currently, 97 people and 27 units of special equipment are involved in the project.
To ensure road safety, an automated traffic control system (ATCS) will be installed here. This equipment complex will allow monitoring the traffic situation in real time.
According to the head of the state company Avtodor, Vyacheslav Petushenko, construction and installation work is being carried out on the section of the M-1 Belarus highway from the 83rd to the 87th km.
“In addition to the construction of the turnaround overpass, we are building overground and underground pedestrian crossings, and have completed monolithic work. Now we are glazing the stairwells and the span structure at the overground pedestrian crossing, and we are doing interior finishing and arranging entrance groups at the underground crossing. In addition, we are continuing to construct nine exits from the expressway, united by distribution lanes. Thanks to them, separate traffic of transit and local transport will be organized, which will significantly increase the safety of drivers and passengers. Also, for the comfort of residents of SNT and populated areas located near the expressway, we are installing noise protection screens with a total area of 10.5 thousand square meters,” noted Vyacheslav Petushenko.
Additionally, at the 86th km of the M-1 “Belarus” it is planned to improve the adjacent territory to the monument to Zoya Kosmodemyanskaya. In particular, road workers will arrange pedestrian paths and parking areas, install outdoor lighting lines.