MIL-OSI Russia: Marat Khusnullin: Reconstruction of the M-1 Belarus highway section is more than half complete

Translation. Region: Russian Federal

Source: Government of the Russian Federation – An important disclaimer is at the bottom of this article.

“We are carrying out systematic work across the country to expand and modernize roadways on key highways and city roads where this is necessary to improve transport accessibility. These measures allow us to increase the capacity of the road network, reduce travel time, reduce accidents and minimize logistics costs. In particular, we are reconstructing the M-1 Belarus high-speed highway from the 66th to the 84th km. We will expand this section from four to six lanes. Currently, specialists are constructing the roadbed at the site; 80% of the excavation work has been completed to date, amounting to about 440 thousand cubic meters. At the same time, work is being carried out to install the road surface. 178 thousand tons of asphalt concrete have already been laid, which is almost half of the planned volume. As of today, the overall readiness of the site is more than 50%. There is still a lot of work ahead, it is important to maintain the current momentum,” said Marat Khusnullin.

The Deputy Prime Minister added that work is underway at the site to install a cable duct for the installation of an automated traffic control system. Barrier and reinforced concrete parapet fencing are being installed; 10 km and 14 km, respectively, have been installed so far. In addition, for safe travel at night, it is planned to install outdoor lighting lines in the dividing strip of the road throughout the site. Currently, the foundations of lighting poles are being installed on the section from the 66th to the 71st km.

According to the Chairman of the Board of the state company Avtodor, Vyacheslav Petushenko, construction and installation work is being carried out on the reconstruction site to erect 12 artificial structures. These are bridges, overpasses and overground pedestrian crossings.

“The main artificial structures at the site are two bridges across the Nara and Kapanka rivers. The bridge across the Nara river is 45% complete. A reinforced concrete monolithic superstructure has already been installed here, the embankment is being filled on the approaches with subsequent installation of transition slabs. The bridge across the Kapanka river is half ready, now it is being prepared for laying asphalt concrete on the junctions and the bridge deck. Also among the key structures are two overpasses. One is part of the interchange at the 74th km, and the other is in the turnaround loop from the village of Lyakhovo at the 72nd km. Their readiness is 70 and 50%, respectively. Small artificial structures are also being built in parallel. These include culverts necessary to ensure uninterrupted water flow under the roadway and prevent flooding, which directly affects road safety,” said Vyacheslav Petushenko.

For the convenience of drivers and passengers, a rest area is being set up at the 74th km of the M-1 “Belarus”. Here, excavation work, road surface construction and storm sewer installation are nearing completion. At the moment, the site is being prepared for the installation of asphalt concrete pavement.

In total, 355 units of equipment and approximately 1,080 people are involved in the reconstructed section.

Please note: This information is raw content directly from the source of the information. It is exactly what the source states and does not reflect the position of MIL-OSI or its clients.