Yuri Trutnev got acquainted with the progress of reconstruction, modernization and operation of infrastructure facilities of the Blagoveshchensk International Airport named after N.N. Muravyov-Amursky (Ignatievo)

During a working visit to the Amur Region, Deputy Prime Minister and Presidential Plenipotentiary Representative in the Far Eastern Federal District Yuri Trutnev familiarized himself with the progress of reconstruction, modernization and operation of infrastructure facilities at the Blagoveshchensk International Airport named after N.N. Muravyov-Amursky (Ignatievo).

Large-scale reconstruction is underway at Blagoveshchensk International Airport. As part of the airfield infrastructure upgrade, a taxiway connecting the new runway with the new apron has been put into operation. Its length is 320 m, and its width, taking into account the reinforced asphalt shoulders, is 46 m. Aircraft servicing has already been accelerated. Thanks to the new taxiway, aircraft can taxi to the parking areas of the new apron under their own power, without waiting to be towed by a tractor. In addition to the taxiway, the airport also received additional parking areas for aircraft. They are located on the new apron, part of which was put into operation in March of this year. Until today, up to three aircraft could be serviced here at a time. The new areas make it possible to place up to five narrow-body aircraft or up to three wide-body aircraft on the apron. A special area for de-icing aircraft has also been equipped here.

Work continues on the construction of the new terminal of the Blagoveshchensk airport. The new airport complex will be 3.5 times larger than the current one. The total area is more than 25 thousand square meters. The throughput capacity is at least 600 passengers per hour on domestic flights and 400 passengers per hour on international flights. The terminal will be equipped with two galleries, each of which will have two jet bridges, as well as comfortable business lounges. Completion of construction and commissioning is scheduled for 2025.

The work on erecting the reinforced concrete structures of the airport complex building has already been completed, the columns and floors of the building have been fully completed, and all the necessary reinforced concrete structures have been installed. The installation of the metal structures of the building is in progress: 745 tons (78%) of the 960 tons of the main structures of the airport complex have been installed, the installation of the main metal structures of the building is planned to be completed in the first ten days of November. The installation of the roof of the building is more than 40% complete. The installation of profile facade systems and the manufacture of double-glazed windows is underway. Engineering equipment for the airport is being purchased. Work is being carried out on laying external networks: the laying of water supply networks has been completed, the piping of water supply chambers is in progress, the laying of the heating main to the airport has been completed, a block-modular boiler house has been delivered and installed at the site, the laying of sewerage and power supply networks on the station square is being completed.