Source: European Parliament
There were several meetings between the Commission and the administration of the Republic of Poland involved in the nuclear power plant investment concerning the procurement aspects of the construction of this nuclear plant.
The Commission was first approached in May 2022 and the last meeting on the procurement dimension of the investment in relation to the selection of the particular technology took place in December 2022.
There was no approval by the Commission of any legal act of the Government of Poland or its entity. The Commission received information concerning the technical conditions that limit choice of nuclear reactors due to the cumulated power generation ranges they could provide.
There was no Commission decision in this regard.