Construction of a transport interchange at the intersection of the Central Ring Road and Dmitrovskoe Highway
In the Moscow Region, construction is underway on a transport interchange at the intersection of the Central Ring Road and Dmitrovskoye Highway. At the site, they have begun to install the foundations of three overpasses of the future road structure complex, Deputy Prime Minister Marat Khusnullin reported.
“When developing the road framework, it is important to link the highways together so that drivers can comfortably build the necessary routes. In addition, a single connection and a sufficient number of interchanges help to free up the most congested areas and save travel time. One of such interchanges is being built near the intersection of the third launch complex of the Central Ring Road and Dmitrovskoye Highway in the Moscow Region. It will improve the accessibility of nearby areas, will increase the capacity of the A-107 Moscow Small Ring Road by redistributing vehicle flows from this highway to the Central Ring Road. The new road facility will also eliminate the intersection of traffic flows at one level and improve traffic safety. Specialists have begun to build the foundations of three overpasses of the future interchange, are rebuilding utility lines, and are working on installing culverts and a roadbed,” said Marat Khusnullin.
The Deputy Prime Minister added that the new infrastructure facility will meet all modern requirements, including being equipped with an automated traffic control system.
On one of the overpasses, 66 m long, all the piles have already been driven in, and workers have begun to install grillages. For the second overpass, 166 m long, 70% of the piles have been driven in, and for the third, 72 m long, 60%.
According to the Chairman of the Board of the state company Avtodor, Vyacheslav Petushenko, the construction of the transport interchange is divided into two stages.
“The first stage is currently being implemented. It includes the construction of four exits with a total length of about 2.7 km with the construction of three overpasses, as well as the reconstruction of a section of the federal highway A-107 “Moscow Small Ring” with a length of about 2.3 km,” noted Vyacheslav Petushenko.
Currently, there are about 150 people and about 60 units of special equipment and dump trucks involved in the project. The commissioning of the transport interchange is planned for 2026.