Sergei Sobyanin opened a new electric depot “Yuzhnoye” of the Zamoskvoretskaya line. Its commissioning became the final stage of the formation of the largest in Russia and one of the largest in Europe complexes for the repair, maintenance and operation of metro cars.
On behalf of the President of the Russian Federation Vladimir Putin, Moscow Mayor Sergei Sobyanin presented the Moscow Metro with the Order “For Valiant Labor”, which recognized the great merits of the metro workforce in strengthening and developing the capital’s transport complex. The award was timed to coincide with the 90th anniversary of the metro.
In addition, 10 new “Moscow-2024” trains ceremoniously entered the Zamoskvoretskaya line. Together with metro employees and invited guests, Sergei Sobyanin rode on the lead train from the depot to the Krasnogvardeyskaya station.
“This year, the Moscow Metro turns 90. It is a respectable age, but the Moscow Metro demonstrates a very young, energetic life, developing, adding new lines, new stations, first-class trains, electric depots, developing in a way that probably no other metro in the world is developing. Today, a new electric depot “Yuzhnoye” is being opened, the largest and most modern in Russia. The Zamoskvoretskaya line of the metro is being replenished with 10 new trains, the most modern. This year, in honor of the metro’s anniversary, in honor of its merits, the President of the Russian Federation signed a decree on awarding the Moscow Metro team with the Order for Labor Valor. This is a well-deserved award. The Moscow Metro is the most intensive in the world, the most accurate, the most reliable, the safest, the cleanest and the most beautiful. And the most beloved by Muscovite passengers,” said Sergei Sobyanin.
The Mayor of Moscow congratulated the entire staff of the capital’s metro, metro builders and everyone who is related to the metro on the award and anniversary.
The head of the Moscow Metro, Viktor Kozlovsky, in turn, thanked the President of Russia for the award and Sergei Sobyanin for his assistance and constant participation in the development of the metro.
“I would like to say a huge thank you to the President of our country, Vladimir Vladimirovich Putin, for the high assessment of our work, our many thousands of people, and personally to you, Sergey Semenovich, for your constant participation, for the development of the Moscow Metro. For the work that you do. The Moscow Metro is ready to continue to fulfill any tasks at a high level,” said Viktor Kozlovsky.
Thanks to the unprecedented construction of new lines and stations, more than 90 percent of Muscovites now live in the service area of the rail frame stations. For comparison: in 2010, this figure was 70 percent. On weekdays, the metro carries more than 8.2 million passengers. The Moscow metro has become a world leader in important indicators. Thus, the accuracy of the schedule is 99.9 percent, the traffic intensity reaches 90-second intervals during rush hours on the most popular lines, a variety of payment methods and customer services are available, which leads to a high level of passenger loyalty.
Development of the capital’s metro
In 2010, city residents built most of the routes through the center. As a result, transfer stations here were overloaded almost all day long, and at peak times, passengers managed to get on far from the first train.
Thanks to the development of the Moscow Metro infrastructure – the opening of new stations and the renewal of rolling stock – every year the trips become faster and more comfortable, many additional transfers and route options appear, the carriages become noticeably freer even during rush hours. There are no more overloaded sections in the metro.
The first stage of the Moscow metro opened on May 15, 1935. It included 11.2 kilometers of lines and 13 stations – from Sokolniki to Park Kultury with a branch to Smolenskaya. Shortly before that, on November 10, 1934, the Severnoye electric depot began operating.
Today, together with the Moscow Central Circle (MCC), the metro has 302 stations (271 metro stations and 31 MCC stations), as well as 23 electric depots, including the Brateevo car repair complex.
Since 2011, 123 stations have been built and reconstructed in Moscow — their total number has increased by almost 1.7 times. New lines have started operating: Nekrasovskaya, Solntsevskaya and Troitskaya. Sokolnicheskaya, Lyublinsko-Dmitrovskaya, Zamoskvoretskaya and a number of other metro lines have been extended. Two new rings (MCC and Big Circle Line) provide convenient transfers and transit along routes without entering the center. In Soviet times, it took almost 40 years to build a network of such a scale.
More than 130 kilometers of the capital’s metro tunnels were laid in five yearsSergei Sobyanin opened full service on the Troitskaya metro line
The Moscow Metro employs over 65,000 workers (almost a third of whom are women), with an average age of 43. The company is represented by more than 200 professions and specialties. The metro workforce includes more than 100 dynasties with a total work experience of over 15 thousand years.
In recent years, the city has been paying special attention to the renewal of its rolling stock. Moscow is the leader among European and American megacities in terms of the rate of renewal of its metro cars. Today, the Moscow Metro fleet has over 6.7 thousand cars of various models, with over 77 percent of them being of the current generation. Since 2010, the average age of metro cars has decreased almost twofold — from 20 to 12 years. By the end of 2025, another 272 Moscow-2024 cars are to be added to the fleet, and in 2030, the share of new trains will be about 90 percent, meaning that modern trains will serve passengers on all metro lines. In addition, the share of domestic components in Moscow-2024 trains has reached almost 95 percent.
Trains created according to the technical specifications of the Moscow Metro are a standard for the metros of other cities and countries. In addition to the capital of Russia, trains based on the Moscow train are supplied to the metros of four cities – Kazan (Russia), Baku (Azerbaijan), Tashkent (Uzbekistan) and Minsk (Belarus).
Most trains in the Moscow metro are serviced under a life cycle contract. These are the Oka, Moskva, Moskva-2020 and Moskva-2024 type trains. The manufacturer’s service company is responsible for timely and high-quality maintenance, train diagnostics, washing and daily cleaning, as well as the readiness of the trains to go on the line.
Electric depot as part of the metro
In addition to performing their main function – parking, scheduled maintenance and washing of rolling stock, electric depots are the basic enterprises of the Moscow Metro for the repair of electric trains and auxiliary production, and also serve to accommodate personnel and equipment of various services. In fact, the electric depot is the technological heart of the metro.
Without the construction of new electric depots, the development of the metro is impossible; they are as important a part of the infrastructure as stations and tunnels.
Since 2011, 13 electric depots have been built and reconstructed as part of the Moscow Metro development program. Thus, eight new ones appeared: Aminyevskoye, Brateevo, Likhobory, Mitino, Nizhegorodskoye, Rudnevo, Solntsevo and Yuzhnoye (Brateevo-2). They service trains on six lines, are equipped with all the necessary equipment and are ready for technical maintenance, periodic and unscheduled repairs of cars. Another five electric depots have been reconstructed. These are Vladykino, Vykhino, Pechatniki, Planernoye and Sokol.
This year, the city plans to complete construction of the Stolbovo (Salaryevo) depot on the Sokolnicheskaya Line. Three more depots are to appear by 2030: Ilyinskoye for the Rublevo-Arkhangelskaya Line, Biryulevskoye for the Biryulevskaya Line, and Troitskoye for the Troitskaya Line.
Sergei Sobyanin: The first metro train arrived at the Stolbovo electric depot under constructionWhere trains spend the night: how metro cars are serviced and repaired at the Krasnaya Presnya depot
Electric depot “Yuzhnoye”
The Yuzhnoye electric depot is the largest in Russia and one of the largest complexes in Europe for the repair, maintenance and operation of wagons.
The Zamoskvoretskaya Line is one of the longest and most popular in the Moscow metro. From 24 stations on the green line, you can make 19 transfers to other metro lines, the Moscow Central Circle (MCC) and the Moscow Central Diameters (MCD). More than 880 thousand trips are made on the line every day. At the most popular times, trains run at intervals of 1.6 minutes.
The last 10 years have been a time of dynamic development of the Zamoskvoretskaya line. From 2015 to 2018, new stations “Tekhnopark”, “Khovrino” and “Belomorskaya” were opened, which improved transport accessibility of five districts of the capital: Khovrino, Levoberezhny, Zapadnoye Degunino, Nagatinsky Zaton and Danilovsky.
In 2023, new tunnels were built in record time on the Kantemirovskaya-Tsaritsyno section. Last year, the first Moskva-2024 train entered service on the Zamoskvoretskaya Line, which marked the beginning of the rolling stock renewal process.
Passengers on the Zamoskvoretskaya Line are transported by 78 trains (624 cars), including 30 trains (240 cars) “Moscow-2024”. On May 21, 2025, another 10 of these most modern trains in the world entered service. Thus, more than 50 percent of the rolling stock on the Zamoskvoretskaya Line has been updated. The process on the green line is planned to be completed in 2025-2026. Both modern Russian “Moscow-2024” trains and the newest “Moscow-2026” trains will run on it. More than 1.8 million residents of 21 districts through which the Zamoskvoretskaya Line passes will receive new and modern rolling stock – their trips will become much more comfortable.
Until 2021, the trains of the Zamoskvoretskaya line were serviced by the Sokol (since 1938), Zamoskvoretskoye (since 1969) and Brateevo (since 2014) electric depots.
However, in 2021, the Zamoskvoretskoye depot was transferred to service the rolling stock of the Big Circle Line of the metro, and now it fully serves the needs of the BCL, and also temporarily accepts trains of the Troitskaya Line.
To replace the decommissioned capacities in the south of Moscow, a new electric depot, Yuzhnoye (Brateevo-2), was built next to the existing depot. As a result, the largest in Russia and one of the largest in Europe infrastructure complexes for the maintenance, repair and operation of metro cars was formed.
“Together with the wagon repair plant, the Yuzhnoye electric depot has surpassed the previous record holder, the Mitino depot, in terms of scale. 46 buildings and structures have been built in Yuzhnoye, and the most modern and technologically advanced equipment has been installed: servicing of trains on the Zamoskvoretskaya line will be fast and high-quality. At the same time, the neighboring wagon repair plant will focus on major and medium repairs of wagons from all over the metro,” Sergei Sobyanin wrote in his
Source: Sergei Sobyanin’s Telegram channel @mos_sobyanin
In the new Yuzhnoye depot, on a site of 13.6 hectares, buildings and structures with a total area of 77.3 thousand square meters were constructed, including a storage and repair building, a motor depot and an electrical centralization post, a compressor station, a warehouse, an administrative and household building and other structures – a total of 46 buildings for various purposes.
The total length of the tracks at the Yuzhnoye depot is about 6.2 kilometers, which can be compared with the section between the Krylatskoye and Strogino stations, the longest in the Moscow Metro.
After reaching its design capacity, the enterprise will create approximately 1.3 thousand jobs.
Along with the modern carriages, a service company from the manufacturer arrived at the Yuzhnoye depot, which will service the new rolling stock (trains Moscow-2024 and Moscow-2026) under a life cycle contract for 30 years of operation.
The staff was provided with the most favorable conditions for efficient work and good rest.
The administrative building has a canteen for 160 people. The locomotive crews’ rest rooms are organized like hotel rooms, and the blocks are equipped with bathrooms. Separate comfortable rooms are provided for female drivers.
There are currently 130 female drivers and assistant drivers working in the Moscow Metro. In addition, about 50 women are undergoing training in the profession. It is planned that female drivers will soon begin working on the Zamoskvoretskaya Line.
The medical service includes pre-trip examination rooms, a doctor, a medical psychologist, a treatment room, a vaccination room, and a recovery room.
There are also a sports hall and a gym with a physical education instructor’s office, an assembly hall and utility rooms (laundry, ironing, storage rooms for special clothing).
After the commissioning of the Yuzhnoye depot, it took over the functions of servicing the Zamoskvoretskaya line, including the new Moscow-2024 series trains, which began carrying passengers in March 2024.
At the same time, the Brateevo depot will become the main car repair complex of the Moscow Metro. Its capacity allows repairing the rolling stock of the Zamoskvoretskaya line, as well as carrying out technically complex repairs of cars of the Nomernoy and Rusich types from other metro lines. In total, up to 850 cars, 8.5 thousand wheels and more than 6.4 thousand engines per year – a record for similar facilities in Russia.
The wagon repair complex will not only be the largest, but also the most modern, with a high level of automation – a conveyor for moving wheel pairs, electric bogies, and CNC machines.
In terms of its scale, the new infrastructure complex, consisting of the Yuzhnoye depot and a wagon repair plant, has surpassed the previous record holder, the Mitino electric depot, which until now was the largest in Russia in terms of capacity. The total area of the complex is 32.2 hectares. The capacity of the complex allows servicing up to 2.4 thousand wagons per year.
Main characteristics of the new infrastructure complex
Depot “Yuzhnoye”:
— capacity — 34 seats for trains;
— night storage — 25 places;
— washing — 12 compositions per day;
— operational maintenance — 30 trains per day;
— technical maintenance — four trains per day;
— turning of wheel pairs — three cars per day;
— current repairs — three trains per month;
— jobs — about 1.3 thousand;
— the total length of the tracks is 6.2 kilometers.
Wagon repair complex “Brateevo”:
— capacity — 11 seats for trains;
— the total length of the tracks is 7.1 kilometers;
— major repairs — 300 cars per year;
— average repairs — 550 cars per year;
— repair of traction electric motors — 6.4 thousand units per year;
— wheel sets — 8.5 thousand pieces per year;
— motor-compressors — two thousand pieces per year.
Please note: This information is raw content directly from the source of the information. It is exactly what the source states and does not reflect the position of MIL-OSI or its clients.
Please Note; This Information is Raw Content Directly from the Information Source. It is access to What the Source Is Stating and Does Not Reflect
https: //vv.mos.ru/mayor/tkhemes/12781050/